Reservations wrong after a MR with three lines of same PO Line

Description

Related to

Test case is:

  • Sysconfig VALIDATE_MATCHING_TO_ORDERED_QTY must be set to N

  • create a PO Line for a product with Qty=20 and complete it

  • then create a material receipt - and using the create lines from - create three times the MR Line for the PO Line created above - that will receive 60 in three different lines

  • complete the Material Receipt

After completing the reservation will be wrongly 20 -> must be zero
The QtyOverReceipt for the lines will be 0, 20, 40 -> must be 0, 20, 20

Regards,

Carlos Ruiz

Environment

None

Activity

Show:
Hiep Lq
May 22, 2017, 5:17 PM

hi , WDYT if we add a read-only tab on "purchase order" to show drafted receipt have line create from (refer to) this purchase order

Carlos Ruiz
May 23, 2017, 1:02 PM

, that sounds useful in some cases. But I think not for core, the way to match PO with Receipt is different depending on business cases. That link can be even destroyed and recreated (deleting the match po record and matching again).