On Request window there are 6 date field which are confusing. Suggesting below label changes for same.
Start Time => Actual Start End Time => Actual Completion Start Date => Ticket Creation Close Date => Ticket Closed Start Plan => Planned Start Complete Plan=>Planned Complete
Environment
None
Attachments
1
Activity
Carlos Ruiz
May 9, 2020 at 6:08 PM
Closing as potential idea without too much interest from community.
Deepak Pansheriya
February 8, 2017 at 7:00 AM
Carlos,
Start Plan and Complete Plan field are presents in iDempiere 3.1 but those are not visible on Request window.
On Request window there are 6 date field which are confusing. Suggesting below label changes for same.
Start Time => Actual Start
End Time => Actual Completion
Start Date => Ticket Creation
Close Date => Ticket Closed
Start Plan => Planned Start
Complete Plan=>Planned Complete